RD3.3: Inspector's Daily Report

(see FM5:12.2)

INSPECTOR'S DAILY REPORT (Facility)
PROJECT TITLE______________
PROJECT NO.________________ REPORT NO._______________
CONTRACT NO. _______________
Date ___________________________

Day: S M T W Th F S

Weather: Clear___ Overcast___ Rain___
Mist___ Wind___ Fog___
Site Condition: Clear___ Muddy___ Dusty___
Other_____________
Temperature Range:_______________________

CONTRACTOR'S LABOR FORCE

Supervision____ Administrative_____ Skilled and Unskilled_____ Other______ Total______

SUBCONTRACTOR'S LABOR FORCE
SUBCONTRACTOR
___________________
___________________
___________________
NO.
_____
_____
_____
SUBCONTRACTOR
___________________
___________________
___________________
NO.
_____
_____
_____
WORK PERFORMED
REMARKS
PHONE CALLS
VISITORS
ORAL INSTRUCTIONS
INSPECTOR'S SIGNATURE

_____________________________________

 

<< Back to Table of Contents