INTRODUCTION

The bidding documents are prepared by the design professional and the Facility during a project's construction documents phase and are assembled by the Facility.

2.1 BIDDING DOCUMENT TYPES

The University uses many types of construction documents. The construction bidding documents are part of the overall construction documents. All construction document models contained in Facilities Manual, Volume 4, have been approved for legal form by the Office of the General Counsel.

2.2 BIDDING DOCUMENT REVIEW

Facilities are responsible for reviewing their own bidding documents, regardless of the estimated construction cost. However, proposed changes to the Instructions to Bidders, and the General Conditions must be reviewed by the Office of the President and the Office of the General Counsel. Detailed review procedures are given in FM4.


Revised February 10, 2012 (Change # FM 12-001-C)