Comparison of Prequalification Systems
COMPARISON ITEMS |
PASS/FAIL |
POINTS |
---|---|---|
Recommended delivery systems |
Basic Lump Sum, Multiple Prime |
Design Build, CM at Risk |
Setting Up |
Minimum requirements for qualifications must be set very carefully. |
Points must be carefully distributed between categories to reflect what is most important to the project. |
Evaluation time |
Takes less time to evaluate. |
Takes more time to evaluate since it requires a team to review and calculate the points. Second step interviews are recommended. |
Protests |
The objective minimum requirements could make it harder for the disqualified bidder to contest the University decision. |
There could be potential for bidder to argue against the points given to them vs. their competitors. |